COU Terminal Project Timeline

This page shows a general timeline of the process to construct a new terminal at Columbia Regional Airport. A green box and paper airplane indicates completed step. A purple box and paper airplane indicates the step is in progress.  A blue box and paper airplane indicates future steps. Future event dates are only timeline place holders and do not represent an actual start/completion date. The timeline will be updated and future events will be updated with actual dates as they are known. 

Thank you for supporting Columbia Regional Airport and we look forward to sharing more information with you as it becomes available. 

 

  • Mar
    Project begins 2, 2015

    March 2, 2015 - Columbia City Council Authorizes Parsons Brinckerhoff (WSP) to Develop Terminal Area Master Plan (TAMP)

    On March 2, 2015, the Columbia City Council approved council bill B45-15, a contract with WSP to develop a TAMP, Stormwater Master Plan and Airport Layout Plan (ALP) update.

  • Feb
      15, 2016

    February 15, 2016 - WSP Provides Update to Council and Airport Advisory Board

    At the February 15, 2016, Columbia City Council Work Session, WSP provided a status update on the report titled, “Terminal Area Master Plan City Council Briefing.”

  • Mar
      22, 2016

    March 22, 2016 - TAMP Interested Parties Open House

    WSP hosted an open house on Tuesday, March 22, at the Activities and Recreation Center (ARC) to provide updated information on the study and accept public comment. 

  • May
      2, 2016

    May 2, 2016 - WSP Presents Update and Recommended Terminal Location Options

    On May 2, 2016, WSP presented the City Council with the Columbia Regional Airport Terminal Master Plan update, and the Columbia City Council supported Alternative 2.

  • Oct
      2, 2017

    October 2, 2017 - TAMP Completed by WSP and Submitted to the Federal Aviation Administration for Approval

    In October of 2017, WSP presented the TAMP to the City of Columbia. The plan described the analyses and assessments conducted during the TAMP process and provided the results of those efforts.  Terminal Area Master Plan – Technical Report Airport Layout Plan Full Size 22×34 Airport Layout Plan 11X17 Appendix A-I Appendix J-L

  • Nov
      30, 2017

    November 30, 2017 - FAA Gives Conditional Approval of the TAMP and ALP

    On November 30, 2017, the FAA issued a letter of conditional approval for the TAMP and Airport Layout Plan (ALP). In the letter, the FAA advised that the Alternative 2 location noted in the TAMP was not the preferred location of the FAA. The FAA felt the new terminal should be midpoint to the main Read More »

  • Dec
      18, 2017

    December 18, 2017 - City Council Shifts Support to New Terminal Location Site 1X

    On December 18, 2017, the Columbia City Council discussed Resolution R186-17 at the regularly scheduled council meeting. Council approved unanimously the resolution and instructed staff to proceed with the Site 1X terminal location, just to the south of the current terminal. Staff will begin this work, which includes submitting a Supplemental Terminal Area Master Plan Read More »

  • Jul
      2, 2018

    July 2, 2018 - City Council Approves Request for Proposals (RFP) for the STAMP and Categorical Exclusion Checklist (CATEX)

    On July 2, 2018, the Columbia City Council approved B98-18 and B99-18 (Requests for Proposals and authorizations) for Burns and McDonnell Engineering, to proceed with the STAMP and CATEX checklists.  RFP Adopted – R99-18 STAMP RFP Adopted – R98-18 CATEX

  • Sep
      7, 2018

    September 7, 2018 - Notice to Proceed (NTP) issued to Burns & McDonnell Engineering, Inc. to Complete and Submit STAMP to the FAA

    A NTP to was sent to Burns & McDonnell Engineering to complete the STAMP and submit it to the the FAA.

  • Sep
      17, 2018

    September 17, 2018 - City Council Authorizes Airport Aid Agreement with the Missouri Department of Transportation to Complete the Master Plan and ALP

    The City Council authorized an airport aid agreement with the Missouri Highways and Transportation Commission for completion of Master Plan and ALP updates for the Columbia Regional Airport. B238-18

  • Dec
      17, 2018

    December 17, 2018 - City Council Supports Design/Build Method for the New Terminal

    On December 17, 2018, staff provided information on three construction methodologies to the Columbia City Council for consideration: Design/Build, Design/Bid/Build and Construction Manager at Risk. Council provided direction to staff to proceed with the Design/Build method for the new terminal.

  • Apr
      4, 2019

    April 4, 2019 - Submission of STAMP Documents to FAA – STAMP Approval

    Beginning in the spring of 2019, the STAMP documents were submitted to the FAA for review and approval. On June 24 the City of Columbia and Columbia Regional Airport received approval of the STAMP from the FAA. 

  • Apr
      15, 2019

    April 15, 2019 - City Council Authorizes Contract with Burns & McDonnell Engineering Company, Inc. to Complete a CATEX of Site 1X

    The City Council authorized a consultant agreement with Burns & McDonnell Engineering Company, Inc. to complete a CATEX. This environmental site review for Site 1X is scheduled to be completed in fall of 2019.  Resolution R56-19 Attachment A to Resolution R56-19

  • Jul
      1, 2019

    July 1, 2019 - Council Approved Owner’s Representative Agreement

    The City Council approved a contract to the Owner’s Representative, who will oversee the Terminal Project on behalf of the city. 

  • Summer
      2019

    Summer 2019 - Architectural and Engineering Process Begins

    Creation of initial architectural and engineering design documents that will be used for the Design/Build Request for Qualifications (RFQ) process.

  • Spring
      2020

    Spring 2020 - Design/Build Contract to be Awarded by City Council

    Details will be posted here as they become available. 

  • Summer
      2020

    Summer 2020 - Shovel in the Ground

    Details will be posted here as they become available. 

  • Ongoing
      2020-2021

    Ongoing 2020-2021 - Construction

    Details will be posted here as they become available. 

  • Winter
      2021

    Winter 2021 - Substantial Completion and Temporary Certificate of Occupancy

    Details will be posted here as they become available. 

  • Spring
      2022

    Spring 2022 - Wheels Up! Grand Opening of New COU Terminal

    Details will be posted here as they become available.